Tracking actual manpower/ressources (actuals)

Learn how to track actual manpower in specter and how it is connected to lookahead planning and documentation within the platform

specter automation avatar
Written by specter automation
Updated over 9 months ago

Explanation Video


Step by Step Overview

🔧 Before You Start

  1. Set up Resources


📆 Tracking Actual Manpower

For Completed Tasks (Past Days)

  1. Open Daily Report

    • Click the daily report icon for a past day.

    • Auto-assigned manpower appears based on planned tasks.

  2. Edit Actual Numbers

    • Click Edit and adjust actual manpower per resource.

    • The total at the bottom updates automatically.

🔸 Manpower is tracked per day and resource type (connected to expense types), not per task. Currently (23.04.2025) it is not possible to track resources on a per task basis.


🔜 For Future Tasks (Upcoming Days)

  1. Bulk-Edit via Plan View

    • Select a date column, then Edit Selected Tasks.

    • Activate Edit Resources, adjust actual manpower.

  2. Changes Update All Related Tasks

    • Editing a resource updates it for all tasks of that type on that day.


📊 In the weekplan

  1. See the Comparison in the weekplan under the "personnel" column

    • Right number = originally set on Resource page

    • Left number = actual manpower